Lakeview Towers
Lakeview Towers
679 S Reed Court
Lakewood, CO
The existing coating was peeling due to inadequate prep by the previous installer and a system that wasn’t properly suited for the surface and anticipated conditions. Additionally, there were conditional issues with excessive exposure to ponding water and snow.
-Mechanically grind the entire surface to remove existing failing coating and prepare the substrate to the proper profile for new
coating
-Remove failing control joints and route cracks in substrate
-Install primer, base slurry coat, texture coat, solid
color top coat and elastomeric joint sealant
"CBRE has successfully assisted HKEX to negotiate the best leasing terms, especially with Hongkong Land for our new lease of office floors at Exchange Square. CBRE has provided professional and innovative advice for the re-structuring of various HKEX's leases so that we can achieve large rental savings."